Scheduling Jobs in Parallel

Your child orders dependent jobs and overlaps independent ones to find the finish time.

8 questions Ages 9-11 Answers hidden until revealed
Report an issue

No account needed. We read every report.

Learning goal

Draw a simple timeline that respects order and shared resources and compare plans.

Ana does job A in 3 min. Ben does job B in 5 min. They start together. How long until both finish?

Hint Look at which job ends later.

  1. 5 mins
  2. 8 minutes
  3. 3 mins
Show answer

Correct answer: A 5 mins

Report an issue

No account needed. We read every report.

Ana does A for 4 min, then B for 3 min. Ben does C for 5 min and starts with her. When is everything done?

Hint Work out Ana's timeline and Ben's timeline separately.

  1. After 5 minutes
  2. After 12 minutes
  3. After 7 minutes
Show answer

Correct answer: C After 7 minutes

Report an issue

No account needed. We read every report.

A takes 2 min. B needs 4 min and C needs 3 min; both start after A, at the same time. How long until all are done?

Hint Add A's time to the longer job that follows it.

  1. 9 minutes
  2. 6 minutes
  3. 4 minutes
Show answer

Correct answer: B 6 minutes

Report an issue

No account needed. We read every report.

One person has two jobs that take 3 min and 5 min, and can only do one at a time. What is the least time needed?

Hint Place both jobs one after the other on one timeline.

  1. 8 minutes
  2. 5 mins
  3. 3 mins
Show answer

Correct answer: A 8 minutes

Report an issue

No account needed. We read every report.

Ana does A for 4 min and B for 6 min, one after the other, using one set of pens. Ben starts C at the same time and takes 2 min. When is everything done?

Hint A and B must take turns with the pens; C can run alongside.

  1. After 6 minutes
  2. After 10 minutes
  3. After 12 minutes
Show answer

Correct answer: B After 10 minutes

Report an issue

No account needed. We read every report.

A takes 4 min and B takes 2 min, side by side. C takes 3 min and starts only after both A and B are done. Total time?

Hint Find when both A and B are done, then add C.

  1. 9 minutes
  2. 5 mins
  3. 7 minutes
Show answer

Correct answer: C 7 minutes

Report an issue

No account needed. We read every report.

Job 3 must wait for job 1. Job 2 can be done at any time. What can a second person do while the first does job 1?

Hint Choose the job that does not depend on job 1's result.

  1. Do job 3 right away
  2. Do job 2
  3. Tick off job 3 as done
Show answer

Correct answer: B Do job 2

Report an issue

No account needed. We read every report.

A takes 3 min, B takes 4 min after A, C takes 6 min alone. Two people. Which plan finishes earliest?

Hint Start the independent job while the A-then-B branch runs.

  1. Wait for C, then start A and B
  2. One person does A, B, C in turn
  3. One does A then B while the other does C
Show answer

Correct answer: C One does A then B while the other does C

Report an issue