Your child orders dependent jobs and overlaps independent ones to find the finish time.
8 questionsAges 9-11Answers hidden until revealed
Report an issue
Learning goal
Draw a simple timeline that respects order and shared resources and compare plans.
1
Ana does job A in 3 min. Ben does job B in 5 min. They start together. How long until both finish?
Hint
Look at which job ends later.
A5mins
B8minutes
C3mins
Show answer
Correct answer:A5mins
Report an issue
2
Ana does A for 4 min, then B for 3 min. Ben does C for 5 min and starts with her. When is everything done?
Hint
Work out Ana's timeline and Ben's timeline separately.
AAfter 5 minutes
BAfter 12 minutes
CAfter 7 minutes
Show answer
Correct answer:CAfter 7 minutes
Report an issue
3
A takes 2 min. B needs 4 min and C needs 3 min; both start after A, at the same time. How long until all are done?
Hint
Add A's time to the longer job that follows it.
A9minutes
B6minutes
C4minutes
Show answer
Correct answer:B6minutes
Report an issue
4
One person has two jobs that take 3 min and 5 min, and can only do one at a time. What is the least time needed?
Hint
Place both jobs one after the other on one timeline.
A8minutes
B5mins
C3mins
Show answer
Correct answer:A8minutes
Report an issue
5
Ana does A for 4 min and B for 6 min, one after the other, using one set of pens. Ben starts C at the same time and takes 2 min. When is everything done?
Hint
A and B must take turns with the pens; C can run alongside.
AAfter 6 minutes
BAfter 10 minutes
CAfter 12 minutes
Show answer
Correct answer:BAfter 10 minutes
Report an issue
6
A takes 4 min and B takes 2 min, side by side. C takes 3 min and starts only after both A and B are done. Total time?
Hint
Find when both A and B are done, then add C.
A9minutes
B5mins
C7minutes
Show answer
Correct answer:C7minutes
Report an issue
7
Job 3 must wait for job 1. Job 2 can be done at any time. What can a second person do while the first does job 1?
Hint
Choose the job that does not depend on job 1's result.
ADo job 3 right away
BDo job 2
CTick off job 3 as done
Show answer
Correct answer:BDo job 2
Report an issue
8
A takes 3 min, B takes 4 min after A, C takes 6 min alone. Two people. Which plan finishes earliest?
Hint
Start the independent job while the A-then-B branch runs.
AWait for C, then start A and B
BOne person does A, B, C in turn
COne does A then B while the other does C
Show answer
Correct answer:COne does A then B while the other does C
Report an issue